Our plant is able to treat material in the form of foil (or grit), supplying as a product 68% gold cyanurate salt.
The process takes place inside a work tank which is placed strictly under the hood and under suction, housed also on the upper floor of the building structure. This will allow, with some modifications, to discharge the liquid of the saturated solutions, inside the crystallization system, which will be placed under them and therefore on the lower level. This crystallizer is wheeled and equipped with a Buckner filter for collecting gold salt.
The work tank will also be equipped with a movable lid, with tilting opening and connected separately to a reflux head in glass, for the condensation of the produced vapors, which will consequently be directed inside the tank to which they are bound. This system avoids decreases in volume in the tank and therefore negative variations in the concentration of the salt in solution, thus automatically guaranteeing the right final title.
Downstream of the process, a liquid treatment system is envisaged for immediate recovery of the residual gold.





- Description
- Ask a question
- Review
Now a days e waste materials are resulting into heavy pollution that can be harmful. But we at delmer are converting the e waste into a useful products.. we are recycling the e waste and producing mining machines which help you the mine the gold. They are made of super quality with less pricing which can be affordable for all
Increasing global technological development has immensely resulted into enhancing production of electronic waste that creates the challenges and opportunities in its recycling. In this review, we focus on the core value of metal resources in the printed circuit boards usually found in end-of-life electronics, the differences between primary mining applications and secondary mining, and the variety of metallurgical separations, in particular those that have the potential to selectively and sustainably recover gold from waste PCBs. It’s a very reliable and sustainable method which can be very useful for electronic waste and can result into a beneficial product
We at delmer provide these products which can to decrease the pollution and can be beneficial to customers.
"THE BENEFITS OF RECYCLING TECHNOLOGICAL WASTE According to research and facts , it is 13 times more costly to extract minerals from natural deposits than it is to recover them from technological waste for the manufacture of new devices. Obtaining minerals like platinum, copper and palladium does not just involve digging them up and processing them, it also requires the use of huge quantities of water and energy. This is where the concept of the circular economy comes in, based on the use of materials from recycled items and less dependence on the virgin resources extraction."
- without aqua regia.
- without cyanide.
- without corrosive/toxic gases/vapours.
- gold alloy with a gold content of at least 55% is refined in a single step to fine gold with a purity level of 99.99%.
- process time 6 to 8 hours.
- no gold required in the electrolyte.
- no spent acid to dispose of.
- low running costs because the electrolyte is re-used.
- fully automated process with process control.
- patented process
Delmer IQ 1 | Delmer IQ 2 | Delmer IQ 5 | |
Quantity in 6-8 hrs | 1 kg | 2 kg | 5 kg |
Power supply | 400 V | 400 V | 400 V |
Power | 0.5 kW | 0.8 kW | 2 kW |
Dimensions (mm) | 120 x 60 x 175 | 140 x 60 x 175 | 180 x 60 x 175 |
Weight | 100 kg | 130 kg | 180 kg |
- Description
- Ask a question
- Review
Fully equipped precious metal assaying laboratories
We supply you with all technical machines required for the equipping of your analytical laboratory. We cover the whole process chain with our high quality components. Your advantage: you have a competent partner for all your laboratory technology and can benefit from our reliable service.
- Description
- Ask a question
- Review
This system can refine 15 to 120 kg of fine silver (99.9%) in 24 hrs.
The modular system can be expanded at any time. One cell for approx. 15 kg of fine silver consists of the following components:
- electrolyte tank 275 l in PP for up to 10 anodes each with 8 kg.
- cathodes made from polished stainless steel
- filter cloths made from acid-resistant fiber
- Drive with scraper
The system requires no special maintenance and can be operated continuously.
The silver to be processed must be melted to anodes which are then hung in the anode holder. The purity of the silver should not be below 70%.
Approx. 15 kg unit tank dimensions: 800 x 1065 x 1470 mm.
Different sizes are available.
SE AG 15 | SE AG 30 | SE AG 45 | SE AG 90 | SE AG 120 | |
Quantity per 24 hrs. approx. | 15 kg | 30 kg | 45 kg | 90 kg | 120 kg |
Power supply | 400 V three-phase | 400 V three-phase | 400 V three-phase | 400 V three-phase | 400 V three-phase |
Power | 4 kW | 6 kW | 10 kW | 12 kW | 18 kW |
Dimensions (mm) | 1600 x 1400 x 1600 | 2400 x 1400 x 1600 | 3200 x 1400 x 1600 | 6000 x 1400 x 1600 | 7600 x 1400 x 1600 |
Weight | 93 kg | 130 kg | 165 kg | 300 kg | 450 kg |
- Description
- Ask a question
- Review
Application areas for this unit:
- Compact, space-saving, modular system. Capacity: from 6 kg fine gold within 24 hours.
- Easy to expand through modular design.
- Starting material min. 990 %o Au.
- Guaranteed fineness 999.9 %o Au.
- 10 anodes, each with 2 kg.
- The complete unit is located under an exhaust hood and in a drain tray.
- Acids and solutions are not conveyed through pressing but by suction (vacuum).
RGE 7 | RGE 15 | RGE 30 | RGE 45 | |
Power supply | three-phase | three-phase | three-phase | three-phase |
Power | 2 kW | 4 kW | 5 kW | 6 kW |
Quantity refinable per tank (every 24 hours) | 6 kg | 12 kg | 24 kg | 48 kg |
Dimensions (mm) | 1200 x 720 x 1900 | 1500 x 720 x 1900 | 1800 x 720 x 1900 | 2100 x 720 x 1900 |
Weight | 120 kg | 185 kg | 220 kg | 260 kg |
- Description
- Ask a question
- Review
We developed the GRC Gold Recovery System especially to recover gold from grinding and polishing sludge, scraps, sweepings and ashes. It goes without saying that the recovery of gold from solutions such as rinsing baths, polishing baths etc. is a matter of course.
The GRC system consists of a completely new concept of an electrolytic cell where the recovery starts with the filtration of sludge in a reactor especially designed for this purpose.
Compared to the commonly used method of boiling the sludge, the GRC system uses aqua regia to achieve a much higher percentage of gold recovery. Another advantage of the GRC system is that the gold inside the reactor is dissolved at room temperature which reduces energy costs and prevents the emission of toxic gases so that a scrubber is not required.
Application areas for this unit: | Advantages: |
|
|
GRC 250 | GRC 750 | |
Quantity per 24 hrs. approx. | 2.5 kg | 7.5 kg |
Power supply | 400 V three-phase | 400 V three-phase |
Power | 4 kW | 6 kW |
Dimensions (mm) | 1600 x 1400 x 1600 | 2400 x 1400 x 1600 |
Weight (unfilled) | 95 kg | 130 kg |
- Description
- Ask a question
- Review
- Compact, space-saving, modular system series. Capacity: 3 to 100 kg precious metal within 8 hours.
- Easy to expand due to modular design.
- Without corrosive/toxic gases/vapors.
- Including agitator motors, heating, condensers, solvent containers in SCHOTT glass, precipitation and filter units, reservoir.
- Dissolving medium aqua Regia ( HNO3 +HCL).
- The complete unit is located under an exhaust hood and in a drain tray.
- Acids and solutions are not conveyed through pressing but by suction (vacuum).
PMR 3 | PMR 6 | PMR 12 | PMR 32 | PMR 100 | |
Power supply | single-phase | three-phase | three-phase | three-phase | three-phase |
Power consumption | 1 kW | 2,5 kW | 5 kW | 8 kW | 14 kW |
Quantity refinable every 8hrs | 3 kg | 6 kg | 12 kg | 32 kg | 100 kg |
Dimensions (mm) | 1200 x 700 x 2000 | 1300 x 700 x 2000 | 1500 x 700 x 2200 | 1500 x 700 x 2200 | 1600 x 700 x 2200 |
Weight | 70 kg | 210 kg | 250 kg | 270 kg | 340 kg |


- Description
- Ask a question
- Review
Technological leader in the field of recycling systems
- Compact, space-saving, modular recycling series.
- Capacity: 2.5 -120 kg precious metal within 8 hours.
- Easily extendable through modular design.
- The dissolving tank angled at 30° rotates. This realizes an excellent mixing process with the precious metal granules continually grinding against each other. This process serves to remove the silver chloride from the alloy surface and then finally dissolves it.
- Heating is not required.
- Condenser in SCHOTT glass.
- Dissolving medium aqua Regia ( HNO3 +HCL).
- The complete unit is located under an exhaust hood and in a drain tray.
- Acids and solvents are not conveyed through pressing but by suction (vacuum).
NEW : The new drum shape (rectangular) enables us to achieve a higher efficiency: The dissolving time of the gold is considerably reduced.
NEW TB 2 | TB 7 | TB 15 | TB 30 | TB 60 | TB 120 | |
Power supply | 400 V three phase | 400 V three phase | 400 V three phase | 400 V three phase | 400 V three phase | 400 V three phase |
Power | 0.3 kW | 0.8 kW | 0.8 kW | 0.8 kW | 2 kW | 5 kW |
Quantity refinable every 8hrs | 2-2,5 kg | 7 kg | 15 kg | 30 kg | 60 kg | 120 kg |
Dimensions (mm) | 1200 x 670 x 1120 | 1400 x 1040 x 2060 | 1950 x 1080 x 2340 | 1950 x 1080 x 2340 | 3200 x 2000 x 3200 | 3600 x 2200 x 3600 |
Weight (approx.) | 80 kg | 250 kg | 350 kg | 400 kg | 550 kg | 650 kg |
- Description
- Ask a question
- Review
GOLD REFINING DELMER IQ
A revolutionary, patented electrolytic process which will influence the technological development in its field. Gold alloys with a gold content of at least 55% are refined in a single step to fine gold with a purity level of 99.99%. No use of toxic or corrosive acids such as aqua Regia or cyanide. The process is fully automated and is controlled by a microprocessor.
During the processing there are no toxic or corrosive gases/vapors. The processing time required to recover fine gold with a purity level of 99.99% is not more than 6-8 hours. The electrolyte used can be re-used up to 30 times. There is no requirement for gold to be in the electrolyte (as was the case with previous electrolyte processes) and therefore the running costs are very low.
- without aqua Regia.
- without cyanide.
- without corrosive/toxic gases/vapors.
- gold alloy with a gold content of at least 55% is refined in a single step to fine gold with a purity level of 99.99%.
- process time 6 to 8 hours.
- no gold required in the electrolyte.
- no spent acid to dispose of.
- low running costs because the electrolyte is re-used.
- fully automated process with process control.
- patented process
Technical Data
Delmer IQ 1 | Delmer IQ 2 | Delmer IQ 5 | |
Quantity in 6-8 hrs | 1 kg | 2 kg | 5 kg |
Power supply | 400 V | 400 V | 400 V |
Power | 0.5 kW | 0.8 kW | 2 kW |
Dimensions (mm) | 120 x 60 x 175 | 140 x 60 x 175 | 180 x 60 x 175 |
Weight | 100 kg | 130 kg | 180 kg |